Sept 2022
Possession
82.2%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Sept 2022) has passed with construction at 82.2%.
Satellite view of this address

Where it is · S NO 65/4/1 PART PLOT NO 11, MURBAD

Promoter

Builder profile

Builder
VASANTI KASHINATH CHAUDHARI

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P51700027105
Status
New
Stage
Certificate Signed
Possession
September 2022
Construction
82.2% complete
Units sold
0 of 0

Similar projects in MURBAD

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how MURBAD compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.