Shree Pinal Project A
CTS No - 4614A, 4615 to 4624, Ghatkopar Rajawadi, 400077
- Possession delayed ~3 yrs. Originally promised Nov 2024, now proposed Apr 2028 per the RERA filing.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Apr 2028 per the RERA filing.
Where it is · CTS No - 4614A, 4615 to 4624, Ghatkopar Rajawadi
Area guide
What it's like to buy in Ghatkopar Rajawadi
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Metro-1 anchor with Godrej's Vikhroli land bank next door.
- Growth drivers:
- Metro 1 interchange, Eastern Express Highway, corporate campuses.
- Who buys here:
- Families wanting east-side connectivity to BKC/Fort.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51800049614
- Status
- New
- Stage
- Certificate Signed
- Possession
- April 2028originally November 2024
- Construction
- 75% complete
- Units sold
- 6 of 19
Keep exploring
Where this project sits, who built it, and how Ghatkopar Rajawadi compares.
In Ghatkopar Rajawadi
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 24 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.