High risk
  • Possession delayed ~7 yrs. Originally promised Dec 2023, now proposed Apr 2031 per the RERA filing.
Satellite view of this address

Where it is · 119,120,121, Kudus (CT)

Promoter

Builder profile

Builder
SUDESH RADHEYSHYAM GUPTA

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P99000011878
Status
Ongoing
Stage
Certificate Signed
Possession
April 2031originally December 2023
Construction
54.5% complete
Units sold
0 of 0

Keep exploring

Where this project sits, who built it, and how Kudus (CT) compares.

Data sourced from the official MahaRERA portal; complaints last synced 7 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.