High risk
  • Possession delayed ~2 yrs. Originally promised Dec 2025, now proposed Oct 2027 per the RERA filing.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Oct 2027 per the RERA filing.
Satellite view of this address

Where it is · SURVEY NO. 25/1/A, PLOT NO. 43, NAVALI

Promoter

Builder profile

Builder
IMPERIAL INFRAREALTY PRIVATE LIMITED

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P99000052942
Status
New
Stage
Certificate Signed
Possession
October 2027originally December 2025
Construction
81.8% complete
Units sold
17 of 21

Similar projects in NAVALI

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how NAVALI compares.

Data sourced from the official MahaRERA portal; complaints last synced 11 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.