High risk
  • Possession delayed ~3 yrs. Originally promised Dec 2018, now proposed Oct 2021 per the RERA filing.
  • Possession date passed. The proposed possession date (Oct 2021) has passed with construction at 76.4%.
Satellite view of this address

Where it is · Gat no 541, Vinayak nagar , Moshi

Promoter

Builder profile

Builder
Shri Labsons Builders and Developers Pvt Ltd

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100010272
Status
Ongoing
Stage
Certificate Signed
Possession
October 2021originally December 2018
Construction
76.4% complete
Units sold
0 of 0