Under construction
SHREE SANDGURU BUILDERS AND DEVELOPERS
MahaRERA P99000012068High risk
SURVEY NO. 115 HISSA NO. 30/2, VIRAR EAST, 401303
Post your property hereOwn or renting out a unit in SHREE SANDGURU BUILDERS AND DEVELOPERS? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in VIRAR EAST come to you.
Jun 2019
Possession
90.9%
Built
0
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Jun 2019) has passed with construction at 90.9%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2019 per the RERA filing.
Satellite view of this address
Where it is · SURVEY NO. 115 HISSA NO. 30/2, VIRAR EAST
Promoter
Builder profile
JAWAHAR MULCHAND BHEDA
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P99000012068
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- June 2019originally June 2018
- Construction
- 90.9% complete
- Units sold
- 0 of 0
Similar projects in VIRAR EAST
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
GAJANAN RESIDENCY
VIRAR EASTPoss. August 2026
HARMONY GRAND
VIRAR EASTPoss. December 2029
RAJIBAI VILLAGE BUILDING NO.2
VIRAR EASTPoss. December 2029
MACCHIMAR SOCIETY
VIRAR EASTPoss. March 2029
SHANTI CLASSIC
VIRAR EAST100% builtPoss. December 20244 complaints
D S HOMES -AARADHYA APARTMENT
VIRAR EAST100% builtPoss. December 2025
DEVI KRUPA
VIRAR EAST90.9% builtPoss. December 2026
RADHEYA ENTERPRISES
VIRAR EAST87.3% builtPoss. December 2026
Keep exploring
Where this project sits, who built it, and how VIRAR EAST compares.
In VIRAR EAST
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.