High risk
  • Possession delayed ~3 yrs. Originally promised Dec 2023, now proposed Nov 2026 per the RERA filing.
  • 20 RERA complaints. 20 complaint records are disclosed against this project on MahaRERA.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Nov 2026 per the RERA filing.

Area guide

What it's like to buy in CHEMBUR

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
NAV DURGA CONSTRUCTION COMPANY

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
B.H.WADHWA & CO.

Browse other projects associated with this architect to compare design and delivery patterns.

No other projects are linked to this architect yet.

Official RERA facts

Registration
P51800017436
Status
New
Stage
Certificate Signed
Possession
November 2026originally December 2023
Construction
91.8% complete
Units sold
73 of 79

Keep exploring

Where this project sits, who built it, and how CHEMBUR,MUMBAI compares.

Data sourced from the official MahaRERA portal; complaints last synced 6 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.