Under construction
SHREE SIDDHI VINAYAK SAMARTH
MahaRERA P52000017396High risk
SURVEY NO 92, PLOT NO 1 AND 2, KARJAT, 410101
Post your property hereOwn or renting out a unit in SHREE SIDDHI VINAYAK SAMARTH? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in KARJAT come to you.
Dec 2021
Possession
36.4%
Built
0
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Dec 2021) has passed with construction at 36.4%.
Area guide
What it's like to buy in KARJAT
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
SHREE SAMARTH RESIDENCY
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52000017396
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2021
- Construction
- 36.4% complete
- Units sold
- 0 of 0
Similar projects in KARJAT
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
BALI IXORA PHASE - 1
KARJATPoss. June 2028
TRULIFE
KARJATPoss. July 2027
VICTORIA HILLS PHASE - 2
KARJATPoss. October 2026
MUDRA AVENUE
KARJATPoss. April 2029
GAJVAKRA PRIME
KARJAT172.7% builtPoss. December 2025
LAXMI ORCHID
KARJAT100% builtPoss. June 2021
SURYA GALAXY PHASE I
KARJAT100% builtPoss. July 2022
ETERNIA SPACE PHASE II
KARJAT100% builtPoss. December 20262 complaints
Keep exploring
Where this project sits, who built it, and how KARJAT compares.
In KARJAT
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 7 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.