SHREE SWAMI SAMARTH
SURVEY NO 39/1A 39/2 45/1C, Chinchvali shekin khopoli, 410202
- Possession delayed ~3 yrs. Originally promised Dec 2024, now proposed Apr 2028 per the RERA filing.
- Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Apr 2028 per the RERA filing.
Where it is · SURVEY NO 39/1A 39/2 45/1C, Chinchvali shekin khopoli
Area guide
What it's like to buy in Chinchvali shekin khopoli
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P52000052210
- Status
- New
- Stage
- Certificate Signed
- Possession
- April 2028originally December 2024
- Construction
- 74.5% complete
- Units sold
- 0 of 17
Keep exploring
Where this project sits, who built it, and how Chinchvali shekin khopoli compares.
In Chinchvali shekin khopoli
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 7 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.