- Possession date passed. The proposed possession date (Dec 2019) has passed with construction at 89.9%.
Where it is · 370 pt, 370/1-158, 356 pt, 365 pt, 365/33 to 50 and 52 non slum plot bearing CST No 370, 371-10, Andheri
Area guide
What it's like to buy in Andheri
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Film City flank with large integrated townships on both flanks.
- Growth drivers:
- Oberoi/NESCO belt, Metro 7, Western Express Highway offices.
- Who buys here:
- Upgraders wanting township amenities without Powai prices.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51800012234
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2019originally December 2018
- Construction
- 89.9% complete
- Units sold
- 0 of 0
Similar projects in Andheri
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Andheri compares.
In Andheri
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.