High risk
  • Possession date passed. The proposed possession date (Apr 2026) has passed with construction at 81.8%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Apr 2026 per the RERA filing.
Satellite view of this address

Where it is · Gat no 17/2 part, Jamdade Estate

Promoter

Builder profile

Builder
Chandrakant Gulab Jamdade

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
Ar Satish waghe

Browse other projects associated with this architect to compare design and delivery patterns.

No other projects are linked to this architect yet.

Official RERA facts

Registration
P52100052917
Status
New
Stage
Certificate Signed
Possession
April 2026originally May 2025
Construction
81.8% complete
Units sold
6 of 10

Keep exploring

Where this project sits, who built it, and how Jamdade Estate compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.