Under construction
SHRI GANESH PARK PHASE-2
MahaRERA P52100018052High risk
GHAT NO 1B, KOLEWADI, 412110
Post your property hereOwn or renting out a unit in SHRI GANESH PARK PHASE-2? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in KOLEWADI come to you.
Apr 2029
Possession
60%
Built
0
Complaints
146
Units
High risk
- Possession delayed ~3 yrs. Originally promised Dec 2025, now proposed Apr 2029 per the RERA filing.
Satellite view of this address
Where it is · GHAT NO 1B, KOLEWADI
Area guide
What it's like to buy in KOLEWADI
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
SANJAY PARSHURAM KUTE
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P52100018052
- Status
- New
- Stage
- Certificate Signed
- Possession
- April 2029originally December 2025
- Construction
- 60% complete
- Units sold
- 118 of 146
Keep exploring
Where this project sits, who built it, and how KOLEWADI compares.
In KOLEWADI
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 7 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.