Under construction
Shri Sai Park
MahaRERA P52100026618High risk
Gat No 330 331, Khed, 410501
Post your property hereOwn or renting out a unit in Shri Sai Park? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Khed come to you.
Dec 2027
Possession
48.2%
Built
0
Complaints
63
Units
High risk
- Possession delayed ~4 yrs. Originally promised Sept 2023, now proposed Dec 2027 per the RERA filing.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2027 per the RERA filing.
Satellite view of this address
Where it is · Gat No 330 331, Khed
Area guide
What it's like to buy in Khed
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
Sachin Bapurao Khupse
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52100026618
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2027originally September 2023
- Construction
- 48.2% complete
- Units sold
- 32 of 63
Similar projects in Khed
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Escape City Ph 2
KhedPoss. December 2027
Imperial Plaza
KhedPoss. June 2029
Empire Business Hub
KhedPoss. July 2029
Shankeshwar World
KhedPoss. October 2030
SHIV SONAI RESIDENCY
KhedPoss. February 2029
Harmony
KhedPoss. June 2028
PRADNYESH PRIME
KhedPoss. April 2030
Shree Jay Ganesh Samrtham
KhedPoss. December 2029
Keep exploring
Where this project sits, who built it, and how Khed compares.
In Khed
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 7 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.