High risk
  • Mortgaged to a lender (₹17.5 Cr). MahaRERA's financial encumbrance declaration shows this project has ₹17.5 Cr secured against a lender — a lender's claim can outrank a buyer's if the promoter defaults.
  • Possession delayed ~2 yrs. Originally promised Dec 2025, now proposed Oct 2027 per the RERA filing.
  • Behind schedule. Possession is due Oct 2027 but construction is only at 0%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Oct 2027 per the RERA filing.
Satellite view of this address

Where it is · Survey No. 313/2/4, 315/1, Pune

Promoter

Builder profile

Builder
SHRIRAM SAMRUDDHI DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100052123
Status
New
Stage
Certificate Signed
Possession
October 2027originally December 2025
Construction
0% complete
Units sold
0 of 0

Similar projects in Pune

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Pune compares.

Data sourced from the official MahaRERA portal; complaints last synced 7 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.