SHUBHARAMBH
64/3/6 64/3/7 64/3/9/2 64/3/9/3 64/3/9/4, Haveli, 411016
- Possession delayed ~3 yrs. Originally promised Mar 2018, now proposed Sept 2020 per the RERA filing.
- Possession date passed. The proposed possession date (Sept 2020) has passed with construction at 90.9%.
Where it is · 64/3/6 64/3/7 64/3/9/2 64/3/9/3 64/3/9/4, Haveli
Area guide
What it's like to buy in Haveli
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Retail-and-BPO hub with dense mid-income housing on both sides.
- Growth drivers:
- Mindspace offices, Link Road retail, Metro 2A.
- Who buys here:
- Mid-income families, first-time buyers.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52100001406
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- September 2020originally March 2018
- Construction
- 90.9% complete
- Units sold
- 0 of 0
Similar projects in Haveli
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Haveli compares.
In Haveli
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 6 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.