Under construction

SHUBHARAMBH RESIDENCY

MahaRERA P52100008772High risk

by AB DEVELOPER

SURVEY NO 448 HISSA NO 26, Man, 411057

Official record
Mar 2018
Possession
29.1%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Mar 2018) has passed with construction at 29.1%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2018 per the RERA filing.
Satellite view of this address

Where it is · SURVEY NO 448 HISSA NO 26, Man

Promoter

Builder profile

Builder
AB DEVELOPER

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52100008772
Status
Ongoing
Stage
Certificate Signed
Possession
March 2018
Construction
29.1% complete
Units sold
0 of 0

Similar projects in Man

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Man compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.