High risk
  • Possession delayed ~1 yr. Originally promised Dec 2020, now proposed Jun 2022 per the RERA filing.
  • Possession date passed. The proposed possession date (Jun 2022) has passed with construction at 90.9%.
Satellite view of this address

Where it is · S No 920 924 925 926, Chikhali

Promoter

Builder profile

Builder
Tulip Developers

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52100002475
Status
Ongoing
Stage
Certificate Signed
Possession
June 2022originally December 2020
Construction
90.9% complete
Units sold
0 of 0

Similar projects in Chikhali

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Chikhali compares.

Data sourced from the official MahaRERA portal; complaints last synced 6 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.