High risk
  • 2 appeals at MahaREAT. 2 complaints against this project have been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
  • Possession delayed ~2 yrs. Originally promised Dec 2024, now proposed Dec 2026 per the RERA filing.
  • 8 RERA complaints. 8 complaint records are disclosed against this project on MahaRERA.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Satellite view of this address

Where it is · 26, Borivali

Area guide

What it's like to buy in Borivali

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

GoregaonUpper-mid

Film City flank with large integrated townships on both flanks.

Growth drivers:
Oberoi/NESCO belt, Metro 7, Western Express Highway offices.
Who buys here:
Upgraders wanting township amenities without Powai prices.

PropPin area guide — editorial, not a RERA disclosure.

Promoter

Builder profile

Builder
SHIVAM PARIVAR DEVELOPERS PVT LTD

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
Space Moulders

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P51800008681
Status
Ongoing
Stage
Certificate Signed
Possession
December 2026originally December 2024
Construction
85% complete
Units sold
131 of 155

Similar projects in Borivali

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Borivali compares.

Data sourced from the official MahaRERA portal; complaints last synced 21 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.