High risk
  • Possession date passed. The proposed possession date (Jun 2021) has passed with construction at 27.3%.
Satellite view of this address

Where it is · 93 P, MOSHI GAOTHAN

Promoter

Builder profile

Builder
SIDDHESHWAR DEVELOPERS AND BUILDERS

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52100016365
Status
New
Stage
Certificate Signed
Possession
June 2021
Construction
27.3% complete
Units sold
0 of 0

Keep exploring

Where this project sits, who built it, and how MOSHI GAOTHAN compares.

Data sourced from the official MahaRERA portal; complaints last synced 6 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.