SIDDHIVINAYAK CROWN
S.196/H.13,9,4/1,3a,b,5,6,7,8,10,11,12.S.197/H.8,10.S.202/H,3p,4/1,13/1,13/2,7S.204/H.35,36, Vasai-Virar City (M Corp), 401305
- Possession delayed ~7 yrs. Originally promised Feb 2022, now proposed Dec 2028 per the RERA filing.
Where it is · S.196/H.13,9,4/1,3a,b,5,6,7,8,10,11,12.S.197/H.8,10.S.202/H,3p,4/1,13/1,13/2,7S.204/H.35,36, Vasai-Virar City (M Corp)
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P99000011070
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2028originally February 2022
- Construction
- 90% complete
- Units sold
- 24 of 53
Similar projects in Vasai-Virar City (M Corp)
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Vasai-Virar City (M Corp) compares.
In Vasai-Virar City (M Corp)
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 24 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.