Signature Residency
by Theme Infraprojects Private Limited
111, 114/1, 114/2A, Patalipada, 400607
- Litigation pending (1). MahaRERA's litigation disclosure lists 1 pending case against this project.
- 2 appeals at MahaREAT. 2 complaints against this project have been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
- Possession date passed. The proposed possession date (Apr 2023) has passed with construction at 90.9%.
Where it is · 111, 114/1, 114/2A, Patalipada
Area guide
What it's like to buy in Patalipada
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
A full city of its own — lakes, malls and township-scale supply along Ghodbunder Road.
- Growth drivers:
- Metro 4/5 corridors, big-brand townships, spillover from Mumbai pricing.
- Who buys here:
- Families upgrading to space and amenities without island-city prices.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P51700008025
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- April 2023originally April 2022
- Construction
- 90.9% complete
- Units sold
- 0 of 0
Keep exploring
Where this project sits, who built it, and how Patalipada compares.
In Patalipada
The developer
Research