High risk
  • Possession delayed ~6 yrs. Originally promised Sept 2021, now proposed Apr 2027 per the RERA filing.
  • Behind schedule. Possession is due Apr 2027 but construction is only at 4.5%.
Satellite view of this address

Where it is · GAT No. 723, 730, Haveli

Promoter

Builder profile

Builder
Silver Touch Developers

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52100020228
Status
New
Stage
Certificate Signed
Possession
April 2027originally September 2021
Construction
4.5% complete
Units sold
80 of 110

Similar projects in Haveli

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Haveli compares.

Data sourced from the official MahaRERA portal; complaints last synced 12 Sept 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.