- Possession date passed. The proposed possession date (Oct 2026) has passed with construction at 90.9%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Oct 2026 per the RERA filing.
Where it is · Survey No 514/13, Nr Tanishk Pulp
Area guide
What it's like to buy in Nr Tanishk Pulp
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Architect
Design profile
Browse other projects associated with this architect to compare design and delivery patterns.
Official RERA facts
- Registration
- P52100051750
- Status
- New
- Stage
- Certificate Signed
- Possession
- October 2026originally June 2026
- Construction
- 90.9% complete
- Units sold
- 5 of 11
Keep exploring
Where this project sits, who built it, and how Nr Tanishk Pulp compares.
In Nr Tanishk Pulp
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 17 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.