High risk
  • Litigation pending (1). MahaRERA's litigation disclosure lists 1 pending case against this project.
  • Possession delayed ~1 yr. Originally promised Oct 2026, now proposed Oct 2027 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Oct 2027 per the RERA filing.
Satellite view of this address

Where it is · S.NO. 196/2, WAKAD

Promoter

Builder profile

Builder
SIYARAM DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
IP ASSOCIATES

Browse other projects associated with this architect to compare design and delivery patterns.

No other projects are linked to this architect yet.

Official RERA facts

Registration
P52100052484
Status
New
Stage
Certificate Signed
Possession
October 2027originally October 2026
Construction
73.2% complete
Units sold
46 of 115

Similar projects in WAKAD

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how WAKAD compares.

Data sourced from the official MahaRERA portal; complaints last synced 6 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.