Under construction

Skyi Manas Lake Phase VIII

MahaRERA P52100052033High risk

by Enerrgia Skyi Ventures LLP

215(P) 217(P) 218 219 220 221 222 223 224(P) 293 294(P), Mulshi, 412115

Official record
May 2026
Possession
48.1%
Built
0
Complaints
48
Units
High risk
  • Litigation pending (1). MahaRERA's litigation disclosure lists 1 pending case against this project.
  • Possession date passed. The proposed possession date (May 2026) has passed with construction at 48.1%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due May 2026 per the RERA filing.
Satellite view of this address

Where it is · 215(P) 217(P) 218 219 220 221 222 223 224(P) 293 294(P), Mulshi

Area guide

What it's like to buy in Mulshi

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
Enerrgia Skyi Ventures LLP

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100052033
Status
New
Stage
Certificate Signed
Possession
May 2026
Construction
48.1% complete
Units sold
48 of 48

Similar projects in Mulshi

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Mulshi compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.