Caution
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2027 per the RERA filing.

Promoter

Builder profile

Builder
SKYWAY DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
DISHA ARCHITECTS

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P52000077751
Status
New
Stage
Certificate Signed
Possession
June 2027
Construction
75% complete
Units sold
12 of 25

Similar projects in NODE- PUSHPAK

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how NODE- PUSHPAK compares.

Data sourced from the official MahaRERA portal; complaints last synced 4 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.