Dec 2018
Possession
50.9%
Built
0
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Dec 2018) has passed with construction at 50.9%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2018 per the RERA filing.
Satellite view of this address
Where it is · Plot No 17 and 22 CTS No 1262 part and 1263 S No 89/1 90/1 91/1, Parvati
Promoter
Builder profile
Kelkar Pinnac Housing LLP
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P52100004563
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2018
- Construction
- 50.9% complete
- Units sold
- 0 of 0
Similar projects in Parvati
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Janaki Prasad
ParvatiPoss. April 2029
Varadshree
ParvatiPoss. July 2028
SATYAM
ParvatiPoss. January 2029
UMANG
Parvati100% builtPoss. December 2017
ANANT
Parvati100% builtPoss. December 2022
MONTECITO Phase II - E Building
Parvati93.2% builtPoss. December 20211 complaint
Dinashree
Parvati90.9% builtPoss. September 2018
Anand Shree Society
Parvati90.9% builtPoss. April 2019
Keep exploring
Where this project sits, who built it, and how Parvati compares.
In Parvati
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 6 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.