Solitaire Business Hub-III-Phase-II,Baner
S No 9/3 9/4 9/5 9/6 9/7 Baner, Haveli, 411045
- Litigation pending (2). MahaRERA's litigation disclosure lists 2 pending cases against this project.
- Mortgaged to a lender (₹125 Cr). MahaRERA's financial encumbrance declaration shows this project has ₹125 Cr secured against a lender — a lender's claim can outrank a buyer's if the promoter defaults.
- 2 appeals at MahaREAT. 2 complaints against this project have been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
- Possession delayed ~1 yr. Originally promised Dec 2025, now proposed Dec 2026 per the RERA filing.
- 24 RERA complaints. 24 complaint records are disclosed against this project on MahaRERA.
Where it is · S No 9/3 9/4 9/5 9/6 9/7 Baner, Haveli
Area guide
What it's like to buy in Haveli
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Architect
Design profile
Browse other projects associated with this architect to compare design and delivery patterns.
Official RERA facts
- Registration
- P52100025108
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026originally December 2025
- Construction
- 71.8% complete
- Units sold
- 149 of 151
Similar projects in Haveli
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Haveli compares.
In Haveli
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 21 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.