- Possession delayed ~4 yrs. Originally promised Dec 2022, now proposed Dec 2026 per the RERA filing.
- 21 RERA complaints. 21 complaint records are disclosed against this project on MahaRERA.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Where it is · 103/507/14, Tilak Nagar
Area guide
What it's like to buy in Tilak Nagar
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Central crossroads reborn via freeway and Metro links.
- Growth drivers:
- Eastern Freeway, Monorail/Metro, BKC proximity at half the price.
- Who buys here:
- BKC-bound professionals and long-time Chembur families.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Architect
Design profile
Browse other projects associated with this architect to compare design and delivery patterns.
Official RERA facts
- Registration
- P51800009157
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2026originally December 2022
- Construction
- 65.5% complete
- Units sold
- 93 of 125
Similar projects in Tilak Nagar
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Tilak Nagar compares.
In Tilak Nagar
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.