Under construction
Stanza
MahaRERA P52100002571High risk
14/1 part, Punawale, 411033
Post your property hereOwn or renting out a unit in Stanza? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Punawale come to you.
Jan 2021
Possession
90.9%
Built
0
Complaints
0
Units
High risk
- Possession delayed ~2 yrs. Originally promised Jul 2019, now proposed Jan 2021 per the RERA filing.
- Possession date passed. The proposed possession date (Jan 2021) has passed with construction at 90.9%.
Satellite view of this address
Where it is · 14/1 part, Punawale
Promoter
Builder profile
Saarrthi Blue Ventures LLP
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52100002571
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- January 2021originally July 2019
- Construction
- 90.9% complete
- Units sold
- 0 of 0
Similar projects in Punawale
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
NB EVO PLAZA
PunawalePoss. June 20301 complaint
SENTOSA EDGE
PunawalePoss. June 2030
RGS Forte Aspire
PunawalePoss. December 2031
Legacy Ekam
PunawalePoss. December 2028
ELITE THE ARC
PunawalePoss. December 2031
F Signature
PunawalePoss. June 2030
Sky Lavish
PunawalePoss. May 2028
108 ASTERA "WING D E & F"
PunawalePoss. December 2030
Keep exploring
Where this project sits, who built it, and how Punawale compares.
In Punawale
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.