High risk
  • Possession delayed ~6 yrs. Originally promised Jun 2019, now proposed Mar 2025 per the RERA filing.
  • Possession date passed. The proposed possession date (Mar 2025) has passed with construction at 90.9%.
Satellite view of this address

Where it is · 9/1, 90/1,2, 90/7/2,, Vasai-Virar City (M Corp)

Promoter

Builder profile

Builder
ERIC INFRASTRUCTURE

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P99000008026
Status
Ongoing
Stage
Certificate Signed
Possession
March 2025originally June 2019
Construction
90.9% complete
Units sold
0 of 0

Similar projects in Vasai-Virar City (M Corp)

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Vasai-Virar City (M Corp) compares.

Data sourced from the official MahaRERA portal; complaints last synced 21 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.