SUDAMA REGENCY BUILDING NO 1, 5
by SHREE SIDDHIVINAYAK ENTERPRISES
156/1B 156/1C 156/1D 156/2 156/3 164, Thane, 400612
- Possession date passed. The proposed possession date (Oct 2018) has passed with construction at 71.4%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Oct 2018 per the RERA filing.
Where it is · 156/1B 156/1C 156/1D 156/2 156/3 164, Thane
Area guide
What it's like to buy in Thane
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51700000953
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- October 2018
- Construction
- 71.4% complete
- Units sold
- 0 of 0
Similar projects in Thane
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Thane compares.
In Thane
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.