High risk
  • Possession delayed ~3 yrs. Originally promised Dec 2023, now proposed Apr 2027 per the RERA filing.
  • Behind schedule. Possession is due Apr 2027 but construction is only at 47.7%.
Satellite view of this address

Where it is · SURVEY NO 34 1A1, Next to Milletary School Campus

Area guide

What it's like to buy in Next to Milletary School Campus

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
Sudarshan Nirman Co

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P51700018847
Status
New
Stage
Certificate Signed
Possession
April 2027originally December 2023
Construction
47.7% complete
Units sold
31 of 60

Keep exploring

Where this project sits, who built it, and how Next to Milletary School Campus compares.

Data sourced from the official MahaRERA portal; complaints last synced 17 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.