- Possession date passed. The proposed possession date (Nov 2022) has passed with construction at 32.7%.
- Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Nov 2022 per the RERA filing.
Where it is · 12/1 ,12/2,12/3/1,12/3/2,12/4,12/5, Pimple Saudagar
Area guide
What it's like to buy in Pimple Saudagar
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52100000325
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- November 2022
- Construction
- 32.7% complete
- Units sold
- 0 of 0
Similar projects in Pimple Saudagar
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Pimple Saudagar compares.
In Pimple Saudagar
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.