  • Possession delayed ~2 yrs. Originally promised Dec 2024, now proposed Apr 2027 per the RERA filing.
  • Behind schedule. Possession is due Apr 2027 but construction is only at 9.1%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Apr 2027 per the RERA filing.
Satellite view of this address

Where it is · Survey No 24 and Hissa No 4, Sagaon

Promoter

Builder profile

Builder
Shreekrupa Construction

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P51700031345
Status
New
Stage
Certificate Signed
Possession
April 2027originally December 2024
Construction
9.1% complete
Units sold
0 of 0

Similar projects in Sagaon

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Sagaon compares.

Data sourced from the official MahaRERA portal; complaints last synced 7 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.