SUMER LIFE CASA
CTS NO- 11APT ,11A/191-402,11D PT,16 ,16/1-92, 19,19/1-28,20PT,25PT,25/1-32 AND 50PT, Kurla, 400072
- Litigation pending (1). MahaRERA's litigation disclosure lists 1 pending case against this project.
- Possession delayed ~4 yrs. Originally promised Jun 2024, now proposed Apr 2028 per the RERA filing.
- 8 RERA complaints. 8 complaint records are disclosed against this project on MahaRERA.
Where it is · CTS NO- 11APT ,11A/191-402,11D PT,16 ,16/1-92, 19,19/1-28,20PT,25PT,25/1-32 AND 50PT, Kurla
Area guide
What it's like to buy in Kurla
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Lakeside planned township with an IT/startup ecosystem.
- Growth drivers:
- Hiranandani stock, IIT-B halo, LBS/JVLR connectivity.
- Who buys here:
- Tech professionals and startup founders.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51800026539
- Status
- New
- Stage
- Certificate Signed
- Possession
- April 2028originally June 2024
- Construction
- 41.6% complete
- Units sold
- 0 of 0
Similar projects in Kurla
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Kurla compares.
In Kurla
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 7 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.