High risk
  • Possession delayed ~5 yrs. Originally promised Dec 2021, now proposed Jun 2027 per the RERA filing.
Satellite view of this address

Where it is · 237, Thane

Area guide

What it's like to buy in Thane

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
Sumit Star Land Developers LLP

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
SWAPNIL AMBRE

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P51700008468
Status
Ongoing
Stage
Certificate Signed
Possession
June 2027originally December 2021
Construction
68.6% complete
Units sold
36 of 78

Similar projects in Thane

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Thane compares.

Data sourced from the official MahaRERA portal; complaints last synced 4 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.