Under construction
Sun Enclave
MahaRERA P52100024848High risk
9/8/1, Haveli, 411051
Post your property hereOwn or renting out a unit in Sun Enclave? List it in seconds — reaches buyers researching this project.Looking to buy or rent here?Post your requirement — sellers & brokers in Haveli come to you.
Dec 2023
Possession
86.4%
Built
0
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Dec 2023) has passed with construction at 86.4%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2023 per the RERA filing.
Satellite view of this address
Where it is · 9/8/1, Haveli
Promoter
Builder profile
Naresh Ramchandra Mittal
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P52100024848
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2023
- Construction
- 86.4% complete
- Units sold
- 0 of 0
Similar projects in Haveli
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Skyi Wild Woods Phase I
HaveliPoss. July 2027
Valley Vista
HaveliPoss. December 2018
Vintage City
HaveliPoss. October 2023
Lambodar Gold
HaveliPoss. December 2021
Emerald City
HaveliPoss. December 2021
7 Peace Villas
HaveliPoss. July 2019
Nivaan Medows
HaveliPoss. December 20263 complaints
NIVAAN MEADOWS
HaveliPoss. December 20269 complaints
Keep exploring
Where this project sits, who built it, and how Haveli compares.
In Haveli
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 23 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.