SUN-VISON SOLITAIRE
Final plot No. 47, CTS Nos. 903 A and B, Andheri, 400057
- 1 appeal at MahaREAT. 1 complaint against this project has been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
- Possession delayed ~3 yrs. Originally promised Mar 2018, now proposed Dec 2020 per the RERA filing.
- Possession date passed. The proposed possession date (Dec 2020) has passed with construction at 60%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2020 per the RERA filing.
Where it is · Final plot No. 47, CTS Nos. 903 A and B, Andheri
Area guide
What it's like to buy in Andheri
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Institutional belt (colleges, airport) with steady society redevelopment.
- Growth drivers:
- Airport economy, Metro 3, education cluster.
- Who buys here:
- Airline/airport professionals, Parle loyalists.
PropPin area guide — editorial, not a RERA disclosure.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P51800001637
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2020originally March 2018
- Construction
- 60% complete
- Units sold
- 0 of 0
Similar projects in Andheri
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Andheri compares.
In Andheri
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 21 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.