High risk
  • Possession date passed. The proposed possession date (Dec 2022) has passed with construction at 89.4%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2022 per the RERA filing.
Satellite view of this address

Where it is · 38, 39, MAKHMALABAD SHIVAR

Promoter

Builder profile

Builder
HASMUKHBHAI JERAMBHAI SUHAGIYA

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P51600015731
Status
New
Stage
Certificate Signed
Possession
December 2022
Construction
89.4% complete
Units sold
0 of 0

Similar projects in MAKHMALABAD SHIVAR

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how MAKHMALABAD SHIVAR compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.