Surya Kirti Heights and Tower
69 hissa no 5 71 hissa no 3 72 hissa no 10 72 Hissa no 11 73 hissa no 4, Virar, 401202
- 2 appeals at MahaREAT. 2 complaints against this project have been escalated to the appellate tribunal (MahaREAT) — a stronger signal than the complaint being merely filed.
- Possession delayed ~8 yrs. Originally promised Dec 2018, now proposed Dec 2026 per the RERA filing.
- 6 RERA complaints. 6 complaint records are disclosed against this project on MahaRERA.
Where it is · 69 hissa no 5 71 hissa no 3 72 hissa no 10 72 Hissa no 11 73 hissa no 4, Virar
Area guide
What it's like to buy in Virar
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
No other projects are linked to this promoter yet.
Official RERA facts
- Registration
- P99000003052
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2026originally December 2018
- Construction
- 81.4% complete
- Units sold
- 106 of 114
Similar projects in Virar
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Virar compares.
In Virar
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.