- Possession delayed ~6 yrs. Originally promised Mar 2021, now proposed Dec 2026 per the RERA filing.
- 6 RERA complaints. 6 complaint records are disclosed against this project on MahaRERA.
- Behind schedule. Possession is due Dec 2026 but construction is only at 39%.
- Promised amenities not started. Clubhouse is at 0% build with possession due Dec 2026 per the RERA filing.
Where it is · Out of Survey No 145/1, 145/3, 149/1 , 149/2, 151, 152, 155/2, Upper Savarkar Nagar, Gangapur Road, Nashik
Area guide
What it's like to buy in Upper Savarkar Nagar
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51600003685
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2026originally March 2021
- Construction
- 39% complete
- Units sold
- 0 of 0
Keep exploring
Where this project sits, who built it, and how Upper Savarkar Nagar, Gangapur Road, Nashik compares.
In Upper Savarkar Nagar, Gangapur Road, Nashik
The developer
Data sourced from the official MahaRERA portal; complaints last synced 21 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.