SWAGAT VILLAGE
S.R.NO. - 63/4, 64/2, 64/3, 64/4, 65/2B., Karjat, 410101
- Possession delayed ~4 yrs. Originally promised Jun 2023, now proposed Jun 2027 per the RERA filing.
Where it is · S.R.NO. - 63/4, 64/2, 64/3, 64/4, 65/2B., Karjat
Area guide
What it's like to buy in Karjat
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52000005559
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- June 2027originally June 2023
- Construction
- 79.5% complete
- Units sold
- 0 of 0
Similar projects in Karjat
Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.
Keep exploring
Where this project sits, who built it, and how Karjat compares.
In Karjat
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 4 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.