High risk
  • Litigation pending (1). MahaRERA's litigation disclosure lists 1 pending case against this project.
  • Possession date passed. The proposed possession date (Dec 2019) has passed with construction at 88.2%.
Satellite view of this address

Where it is · SECTOR 17 PLOT NO 2, Ramsheth Thakur International Sports Complex

Area guide

What it's like to buy in Ramsheth Thakur International…

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
MANGALAM DEVELOPER

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52000021121
Status
New
Stage
Certificate Signed
Possession
December 2019
Construction
88.2% complete
Units sold
0 of 0

Keep exploring

Where this project sits, who built it, and how Ramsheth Thakur International Sports Complex compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.