High risk
  • Possession delayed ~2 yrs. Originally promised Jul 2018, now proposed Oct 2020 per the RERA filing.
  • Possession date passed. The proposed possession date (Oct 2020) has passed with construction at 27.3%.
Satellite view of this address

Where it is · 731, Mahalunge

Promoter

Builder profile

Builder
SWASTIK INFRA

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P52100008050
Status
Ongoing
Stage
Certificate Signed
Possession
October 2020originally July 2018
Construction
27.3% complete
Units sold
0 of 0