High risk
  • Possession delayed ~2 yrs. Originally promised Feb 2020, now proposed Aug 2022 per the RERA filing.
  • Possession date passed. The proposed possession date (Aug 2022) has passed with construction at 87.9%.
Satellite view of this address

Where it is · SrNo 53, SrNo 1/1A/1A/1/1,, Dhareshwar Temple

Promoter

Builder profile

Builder
Dhankawade Pokale Developers

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52100001405
Status
Ongoing
Stage
Certificate Signed
Possession
August 2022originally February 2020
Construction
87.9% complete
Units sold
0 of 0

Keep exploring

Where this project sits, who built it, and how Dhareshwar Temple compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.