High risk
  • Possession delayed ~3 yrs. Originally promised Dec 2020, now proposed Dec 2023 per the RERA filing.
  • Possession date passed. The proposed possession date (Dec 2023) has passed with construction at 69.5%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2023 per the RERA filing.
Satellite view of this address

Where it is · 3989,3990,3991,3992, Shastri Nagar

Promoter

Builder profile

Builder
RADHIKA SHELTERS

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P51700016283
Status
New
Stage
Certificate Signed
Possession
December 2023originally December 2020
Construction
69.5% complete
Units sold
0 of 0

Similar projects in Shastri Nagar

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Shastri Nagar compares.

Data sourced from the official MahaRERA portal; complaints last synced 6 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.