Under construction

THARWANI SOLITAIRE PHASE IV

MahaRERA P51700030172High risk

by ANIL HARDASMAL THARWANI

8/1,8/2,12/1 -12/7, 13/1,13/2,14/1-14/4, SHAHAD, 421301

Official record
Jul 2026
Possession
73.2%
Built
0
Complaints
208
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Jul 2024, now proposed Jul 2026 per the RERA filing.
  • Possession date passed. The proposed possession date (Jul 2026) has passed with construction at 73.2%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Jul 2026 per the RERA filing.
Satellite view of this address

Where it is · 8/1,8/2,12/1 -12/7, 13/1,13/2,14/1-14/4, SHAHAD

Area guide

What it's like to buy in SHAHAD

Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.

Promoter

Builder profile

Builder
ANIL HARDASMAL THARWANI

View the promoter’s full developer profile and other projects under the same builder group.

Architect

Design profile

Design
DINESH BAJAJ

Browse other projects associated with this architect to compare design and delivery patterns.

No other projects are linked to this architect yet.

Official RERA facts

Registration
P51700030172
Status
New
Stage
Certificate Signed
Possession
July 2026originally July 2024
Construction
73.2% complete
Units sold
85 of 208

Similar projects in SHAHAD

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how SHAHAD compares.

Data sourced from the official MahaRERA portal; complaints last synced 14 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.