THE ADDRESS BLDG. NO. 1
by STRAWBERRY CONSTRUCTIONS PVT. LTD.
407/3,411/3,6,9,412/1,2,4,6,413/3A,3B,4,5P,6,7,414/1A,2A,2B,2C,415/2,3,4 OF VILLAGE NAVGHAR, BEVERLY PARK, MIRA ROAD (E), 401107
- Litigation pending (4). MahaRERA's litigation disclosure lists 4 pending cases against this project.
- Possession delayed ~5 yrs. Originally promised Dec 2023, now proposed Dec 2028 per the RERA filing.
Area guide
What it's like to buy in BEVERLY PARK
Tap any point for how it was derived. IGR points are computed from real government property-registration records; RERA points come from this project's own MahaRERA filing; EDITORIAL points are PropPin's own area judgement, not data.
Promoter
Builder profile
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P51700018632
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2028originally December 2023
- Construction
- 6.4% complete
- Units sold
- 16 of 156
Keep exploring
Where this project sits, who built it, and how BEVERLY PARK, MIRA ROAD (E) compares.
In BEVERLY PARK, MIRA ROAD (E)
The developer
Research
Data sourced from the official MahaRERA portal; complaints last synced 4 Aug 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.