Under construction

THE CAPITAL

MahaRERA P52100032756Caution

by F5 Realtors

S. No. 153A/1 to 4/1/1 and 153A/1 to 4/1, Haveli, 411028

Official record
Oct 2027
Possession
80.9%
Built
0
Complaints
326
Units
Caution
  • Possession delayed ~3 yrs. Originally promised Dec 2024, now proposed Oct 2027 per the RERA filing.

Promoter

Builder profile

Builder
F5 Realtors

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Architect

Design profile

Design
Shailesh Dandane

Browse other projects associated with this architect to compare design and delivery patterns.

Official RERA facts

Registration
P52100032756
Status
New
Stage
Certificate Signed
Possession
October 2027originally December 2024
Construction
80.9% complete
Units sold
182 of 326

Similar projects in Haveli

Other MahaRERA-registered projects in the same locality — useful for a like-for-like comparison.

Keep exploring

Where this project sits, who built it, and how Haveli compares.

Data sourced from the official MahaRERA portal; complaints last synced 17 Oct 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.